Florida Power &
Light Company
Turkey Point Nuclear Power Plant
Spring Outage 2005
CFS Job # 4099
Subject: COPES-VULCAN (FCV 4-478 "A" Feed Regulation Valve)
Job Scope:
Welding and machining repair of two simultaneously timed sets of in-body
internal valve threads. The new in-body internal valve threads are
machined to accept a new standard COPES-VULCAN Cage.
Equipment Overview: CFS replicated an exact "mock-up" to
demonstrate and prove all processes before performing the actual on-site
repair. CFS designed, engineered, manufactured and tested two state of
the art machines for the subject valve. The first, a "boring and
facing" machine, was used to do initial and final machining. The second
machine was utilized for "threading" only. CFS also modified a TGAW
welding system utilizing a specialty welding front end with oscillator
interchange.
Job Overview: After proving the successful "mock-up"
demonstrations, CFS mobilized to job site. Site specific training,
safety training and in processing was the first order of business. Next,
the equipment was staged and readied. The valve was then inspected and
"As Found" dimensions taken. The initial machining process,
"undercutting to clean metal", was performed by the specialty "boring
and facing" machine. Next, the valve was preheated to 400 degrees
Fahrenheit and the TGAW welding system set into place. The first area to
be welded was 14 inches below valve opening and at a diameter of 12
inches. The second area was 9 inches below the first and at a
diameter of 11.5 inches. After the appropriate amount of weld build up,
a post weld heat treatment (PWHT) was performed. The valve then needed
to cool before the "boring and facing" machine could be reinstalled. The
new weld was then re-machined to specific sizes according to FPL
Engineering. The land distance between the new in-body internal valve
threads had a tolerance of plus or minus one thousands of an inch
(0.001") The final process was to machine the actual threads the new
standard COPES-VULCAN Cage would have to screw into. These new threads
(12 threads per inch) needed to be in perfect timing. The "threading
machine" has a continuous thread spindle to achieve this consistency.
After the threads were machined the COPES-VULCAN Cage was successfully
installed. In addition to the internal valve threads, CFS re-machined
the valve opening surface "flange" and repaired one adjacent stud hole.
Schedule:
Continental Field Systems prides itself on being able to engineer
solutions quickly for its customers. This should be evident by the time
line shown below.
- Monday
03/14/05 began developing thread machining concept for customer
- Thursday
03/31/05 received purchase order
- Thursday
03/31/05 began final design, engineering, manufacturing and testing
on threading machine
- Tuesday
04/19/05 finalized on-site procedure and schedule
- Sunday
4/24/05 traveled to site
- Saturday
5/14/05 finished job
|



|